Current work 3 quarter 2015

Current work 3 quarter 2015

Купить участок, дом в Одессе -                                     Current work 3 quarter 2015

September 2015

  1. Major repair of buildings located at the second scenic viewpoint (toilet, dressing rooms, storage space for umbrellas and sunlounger): Reroofing of buildings, restoration of balustrade, refurbishment of interiors.
  2. Partial renovation of fences of sports grounds located on the quay.
  3. Partial laying of paving slabs at the second and first scenic viewpoints.
  4. Complete replacement of sand on the volleyball court (Naberezhna str.)
  5. Repair of roads at the connection point of the quay with the Eastern, Central and Western slopes.
  6. Emergency repair of outdoor lighting on the Eastern and Central slopes.
  7. Partial repair of storm sewage system and build-up of stormwater gutter walls.
  8. For high-quality drainage of rain and melt liquid from the roads a drainage system was developed on the West slope.
  9. The following regular works on the cottage community area maintenance were performed during the second quarter:

 - daily cleaning of streets, both manual and mechanical;

- comprehensive green planting management in public areas;

- regular removal of household waste.

  1. To implement a high level of security within the cottage community territory, the following activities were carried out during the 3th quarter:

- patrolling the area;

- round-the-clock duty of mobile rapid response team;

- round-the-clock service of checkpoint;

- outdoor video surveillance of the streets and public areas of the cottage community;

- daily walk around inspection of the reserve adjacent to the cottage community in order to identify unauthorized fire sources;

- repair of the fence around the perimeter of the cottage community.

  1. During the third quarter of 2015, to ensure smooth and trouble-free operation of utilities a scheduled preventive maintenance of utilities, pumping stations and transformer substations was performed:

 

Gravity sewerage - the works were performed on a section of 1,206 lm of 11,025 lm Pipes were checked for clogging and maintaining the calculated slope. Blockages were removed. Sections with deviations were restored.

Force main sewerage - the works were performed on a section of 1,970 lm of 11,250 lm. Sewerage was checked for integrity. Damaged pipe sections were repaired. The protected area of pressure header pipeline was inspected for deviations from the requirements of the State Building Codes of Ukraine. Sections with deviations were restored. Shutoff valves has been adjusted.

Water supply system - the works were performed on a section of 2,822 lm of 14,010 lm. Pressure testing was carried out to detect water leaks.

Cable power lines (10 kV), supplying - Cable runs and channels were inspected. Preventive testing was carried out. Communication devices 10 kV were adjusted. Supporting insulation was cleaned from dirt.

Cable power lines (10 kV) - the works were performed on a section of 935 lm of 5,215 lm. Lopping has been carried out on the line with voltage disconnection. Supporting insulation has been inspected for damage. Disconnectors were adjusted - 3 pcs.

Cable power lines (0.4 kV) - the works were performed on a section of 3,605 lm of 21,323 lm. The resistance, ground loop and phase "0" circuit were measured. Communication equipment was adjusted. Contact groups were tightened.

Overhead lines (10 kV), off-take - the works were performed on a section of 19,190 lm of 21,323 lm. The resistance, ground loop and phase "0" circuit were measured. Communication equipment was adjusted. Contact groups were tightened.

Overhead lines (10 kV) - the works were performed on a section of 120 lm of 1,935 lm. Check for branches on the line. Supporting insulation has been inspected for damage. Disconnectors were adjusted.

Transformer substations - the works were performed on 9 pcs. of 11 pcs. Power transformers and switches were refilled with oil. Supporting insulation was cleaned. Contact groups were tightened. The scheduled replacement of current transformers 200/5 in electric power fiscal metering system TP 523 has been carried out.

Sewerage pump stations - the works were performed on 5 pcs. of 13 pcs. The secondary switching networks of pump group control panel were checked.

Inspection and scheduled preventive maintenance of gravity sewerage line and connection beams in Pryberezhna str. on a section of 697 lm.

 Inspection and scheduled preventive maintenance of adjustment wells and pressure headers at SPS 4, SPS 5.

 Water supply pipeline with a length of 883 lm was pressure tested to detect water leaks in the following areas:  1st, 2nd, 3rd Horikhova streets. In the same area 20 connection wells were inspected and all the necessary scheduled preventive maintenance works have been performed.

 Water supply pipeline with a length of 654 lm was pressure tested to detect water leaks in the following areas:  Horikhova, Dzerkalna streets. In the same areas the following was inspected: 1 fire hydrant and 9 connection wells, all the necessary scheduled preventive maintenance works have been performed.

 Inspection and scheduled preventive maintenance of gravity sewerage line and connection beams in Lazurna str. on a section of 509 lm.

 Inspection and scheduled preventive maintenance of adjustment wells and pressure headers at SPS 10, SPS 11, SPS 12.

 Repair of gravity sewerage line to Sewerage Pump Station (SPS) 11 (Horikhova str.).

An inspection and scheduled preventive maintenance of sewerage stations have been performed in Morska and Vitrylna streets.

 Water supply pipeline with a length of 1,285 lm was pressure tested to detect water leaks in the following areas:  Morska and Vitrylna streets. In the same area 5 connection wells were inspected and all the necessary scheduled preventive maintenance works have been performed.

Спасибо за заявку!
Мы свяжемся с Вами в ближайшее время

To order presentation

Get your invitation to visit the object (area near the sea, neck of the woods or prepared at home) in the gated community “Pine beach”

Name*:
Your phone number:
Your e-mail:
Select a convenient time for You:

*We guarantee that Your data will not be disclosed to third parties and is used only to contact You

Ask question

Name*:
Your phone number:
Your e-mail:
Your question:

*We guarantee that Your data will not be disclosed to third parties and is used only to contact You

Вверх